top of page

Engineering Projects Update- January 2019


Andre Monnot

Sewer Rehabilitation Program:

  • Gravity Collection Rehabilitation Project is 75% design complete. Entirety of identified defects within overflow-prone basins will be within budget. Approach to isolated issues is being reviewed to maximize the area of Town treated.

  • Lift Station Rehabilitation Project is 25% design complete, opinion of construction cost remains within $1,799,700 budget. Design completion is anticipated by April 2019.

  • Construction contingency of $100,900 is held in reserve.

  • Utility GIS Survey is complete, computer GIS layer generation is in progress. Operational map available through web interface is still anticipated in February 2019.

  • Pearl St. Lift Station Force Main Upgrade design will be submitted to LA Dept. of Health this week for review and approval.

Harrison Extension:

Wetland delineation complete, Jurisdictional Determination request sent to Corps.

DOTD Utility Extension:

Pipe work is complete, lift station construction is 85% complete.

EndFragment

EndFragment

Featured Posts
Recent Posts
Archive
Search By Tags
bottom of page